MAJOR EXPERIENCE |
Sl No |
Name & Address of Client |
End User |
Brief Description of Work |
Order Date |
Value of Contract |
Year of Completion |
1 |
Fabtech Projects & Engineers Ltd |
HPCL Visakh Refinery |
Design, Supply, Installation and Heat Dry of Refractory Materials in SRU Unit |
20-Dec-12 |
Rs. 72 Lacs |
Oct 2013 |
2 |
Radiant Engineers |
BPCL Kochin Refinery |
DISMANTLING and INSTALLATION OF REFRACTORY LINING IN RFCC |
12-Oct-12 |
Rs. 65 Lacs |
Dec 2012 |
3 |
NEOSTRUCTO CONSTRUCTION LTD |
HPCL Mumbai Refinery |
COMPLETE REFRACTORY LINING IN DHDT HEATER (CASTABLE, CERAMIC FIBRE) |
04-Mar-11 |
Rs. 42 Lacs |
Sep 2012 |
4 |
IOCL Digboi Refinery |
Digboi Refinery |
Dryout & Installation of Refractory Materials in PG Boiler |
21-Mar-12 |
Rs. 21 Lacs |
April 2012 |
5 |
NEOSTRUCTO CONSTRUCTION LTD |
CAIRN Energy Pty Ltd |
Supply & Installation of Insulation Materials |
07-Feb-12 |
Rs. 105 Lacs |
Aug 2012 |
6 |
EASSAR PROJECTS (I) Ltd |
ESSAR OIL LTD, Jamnagar |
INSTALLATION OF REFRACTORY LINING IN HMU & DHDT HEATER, REFORMER EXCHANGER |
02-Jul-10 |
Rs. 92 Lacs |
Dec-11 |
7 |
INDIAL OIL CORPORATION LTD MATHURA Refinery |
Mathura Refinery |
DISMANTLING, INSTALLATION & DRY OUT OF REFRACTORY LINING IN RISER SECTION IN FCCU |
05-Sep-11 |
Rs. 26.5 Lacs |
Oct-11 |
8 |
NEOSTRUCTO CONSTRUCTION LTD |
BPCL Kochin Refinery |
COMPLETE REFRACTORY LINING OF SULPHUR PIT & CONVERTER |
13-Jan-10 |
Rs. 92.5 Lacs |
Aug 2010 |
9 |
NEOSTRUCTO CONSTRUCTION LTD |
BPCL Kochin Refinery |
COMPLETE REFRACTORY LINING AND DRY OUT OF SULPHUR RECOVERY UNIT |
13-Jan-10 |
Rs. 27.5 Lacs |
May 2010 |
10 |
NEOSTRUCTO CONSTRUCTION LTD / KAFER PUNJ LLOYD LTD |
HPCL Visakh Refinery (AP) |
DISMANTLING & INSTALLATION OF REFRACTORY LINING IN FCCU UNIT |
23-Jun-10 |
Rs. 77.6 Lacs |
Oct 2010 |
11 |
INTERNATIONAL STELL SERVICES INC |
HANDAN IRON & STEEL COMPANY |
SUPERVISION OF ROASTER REFRACTORY LINING |
22-Dec-09 |
Rs. 3.5 Lacs |
April 2010 |
12 |
KSFL Sahajanpur |
KSFL Shajanpur (UP) |
Complete Dismantling & Installation of Burner Block, CF Module in Arch and Primarry Reformer, Secondary Reformer, Cold Collector |
17-Apr-12 |
Rs. 60 Lacs |
Oct 2012 |
13 |
Indo Gulf Fertilizers Ltd |
Indo Gulf Fertilizers Ltd |
Dismantling & Installation of Refractory Materials in Primary Reformer, Secondary Reformer, Cold Collector |
07-Mar-12 |
Rs. 24.14 Lacs |
April 2012 |
14 |
Kanpur Fertilizers and Cerment Ltd |
Kanpur Fertilizers and Cerment Ltd |
Complete Dismantling & Installation of Refractory Lining in Various Parts of Primarry Reformer |
23-Nov-11 |
Rs. 18 Lacs |
Jan 2012 |
15 |
Gujrat Narmada Valley Fertilizers Company Ltd |
GNFC, Bharuch |
Installation of Refractory Materials for Reformer, Ducting and Other Equipments |
25-Oct-11 |
Rs. 34.2 Lacs |
July 2012 |
16 |
BRAHMAPUTRA VALLEY FERTILIZER CORPORATION LTD |
BRAHMAPUTRA VALLEY FERTILIZER CORPORATION LTD |
DISMANTLING & INSTALLATION OF REFRACTORY LINING IN REFORMER |
09-Jun-11 |
Rs. 27.5 Lacs |
Nov-11 |
17 |
NEOSTRUCTO CONSTRUCTION LTD |
KSFL Shajanpur (UP) |
DISMANTLING & INSTALLATION OF FIELD JOINTS REFRACTORY LINING IN RG BOILER |
22-Mar-11 |
Rs. 3.75 Lacs |
April 2011 |
18 |
TATA CHEMICALS LTD |
TATA CHEMICALS LTD |
DISMANTLING & INSTALLATION OF REFRACTORY LINING IN REFORMER |
12-Jul-10 |
Rs. 16 Lacs |
Aug 2010 |
19 |
IFFCO LTD |
IFFCO LTD- Aonla Unit |
DISMANTLING & INSTALLATION OF REFRACTORY LINING IN R G BOILER, REFORMER |
02-Apr-10 |
Rs. 10 Lacs |
April 2010 |
20 |
Calderys India Refractories Ltd |
INDOGULF FERTILISERS - Jagdishpur (UP) |
DISMANTLING & INSTALLATION OF REFRACTORY LINING IN R G BOILER |
31-Mar-10 |
Rs. 16 Lacs |
April 2010 |
21 |
Larsen & Toubro Ltd |
Koradi Thermal Power Station |
Installation of Refractory Materials in 660MW CFBC Boiler Unit |
15+03-2013 |
Rs. 23 Lacs |
|
22 |
Lafarge India Pvt Ltd |
Sonadi Cement Plant |
Refractory Lining in Kiln, Cooler , Preheater |
16-May-13 |
Rs. 80 Lacs |
July 2013 |
23 |
Larsen & Toubro Ltd |
Raj West Power Ltd |
Installation of Refractory Materials in 135 TPH CFBC Boiler Unit |
28-Mar-12 |
Rs. 100.6 Lacs |
Oct 2012 |
24 |
CASTWELL INDUSTRIES |
Grasim Industries Ltd |
COMPLETE REFRACTORY LINING IN 2 X 100 TPH CFBC BOILER |
23-May-12 |
Rs. 30.10 Lacs |
Dec 2012 |
25 |
NEOSTRUCTO CONSTRUCTION LTD |
CAIRN Energy Pty Ltd |
Supply & Installation of Insulation Materials |
07-Feb-12 |
Rs. 105 Lacs |
Aug 2012 |
26 |
NAFTO GAZ PVT LTD |
HPCL MITTAL ENERGY LTD - Bhatinda (PB) |
SUPPLY OFVERMICULLITE & M20 GRADE FIREPROOFING MATERIALS IN EQUIPMENT & STRUCTURE |
31-Mar-11 |
Rs. 42 Lacs |
Feb 2012 |
27 |
NAFTO GAZ PVT LTD |
HPCL MITTAL ENERGY LTD - Bhatinda (PB) |
SUPPLY OF PAINTING MATERIALS |
18-May-10 |
Rs. 82 Lacs |
Feb 2012 |
28 |
NAFTO GAZ PVT LTD |
HPCL MITTAL ENERGY LTD - Bhatinda (PB) |
APPLICATION OF INSULATION MATERIALS |
06-Jul-10 |
Rs. 128 Lacs |
Feb 2012 |
29 |
NAFTO GAZ PVT LTD |
HPCL MITTAL ENERGY LTD - Bhatinda (PB) |
SUPPLY OF INSULATION MATERIALS |
06-Jul-10 |
Rs. 389 Lacs |
Feb 2012 |
30 |
NAFTO GAZ PVT LTD |
BORL - Bina (MP) |
APPLICATION OF INSULATION MATERIALS |
05-Sep-09 |
Rs. 89 Lacs |